BRIEF
SiBCAS were appointed to supply and install a Modular Building as office accommodation to house Operations staff for Network Rail.
PROJECT SCALE
Size: 60`x 32` Double Stacked – 2no External Staircase
BUILDING USE
SiBCAS worked closely with the site manager, going over every detail to ensure all their requirements were being met.
SiBCAS cleared and moved the existing containers that were already on the site. After the client visited the BBV Shenkar building SiBCAS began the project providing modular office accommodation.
We were required to provide waste solution which included septic tanks due to there being no previous connection to the foul drain.
CHALLENGES
The modular building was successfully installed and completed on time, resulting in the consideration of a second phase due to the client being so pleased with the building. The client also contemplated purchasing the building.
OUTCOME
The building was delivered and handed over on budget and earlier than the client expected. The on-site management and planning were a great success leaving an extremely satisfied customer.