Rolls Crescent Primary School – Music Classroom
THE BRIEF
In partnership with both Manchester City Council City Technical Services and Manchester Working, SiBCAS were chosen to supply an L2a compliant new music room for the school. The classroom, access ramps and steps were required to be fully DFA2 Compliant. SiBCAS designed foundations which were prepared by Manchester Working, with fire & intruder alarms extended from the existing systems in the school.
PROJECT SCALE
- Size: 7.3m x 12.0m
- Timescale: 4 weeks manufacture plus 2 weeks on site
- Hire period: 7 years
BUILDING USE
Music Room
CHALLENGES
- Weekend delivery only as this is a very popular school in a busy area of Manchester.
- 120 Tonne crane with contract lift undertaken to overcome the difficult position on site.
OUTCOME
The whole project was delivered on schedule and within budget. The school are now able to provide the much missed music teaching lessons in the correct learning environment essential to modern teaching
TESTIMONIAL
The Sibcas team were proactive in providing us with high quality, fit for purpose accommodation, which was delivered on time. I would recommend them without hesitation’ Kay Roche