• Morpeth Bypass, Northgate Site

    Portable Office installation for a large scale construction project.

whatever type of project or size we can bring a fresh eye to any modular accommodation

Project Office Space UK – Morpeth Bypass Northgate Site

THE BRIEF

SiBCAS were asked to provide a number of modular project offices and welfare facilities for Carillion – one of the UK’s leading construction companies – during the construction of the new multi million pound A1 bypass at Morpeth. The portable offices were to be installed with minimal disturbance to the farmers in the area.

PROJECT SCALE

  • Size: 36.6m x 9.75m 2 storey
  • Timescale: approximately 8 weeks
  • Hire period: 90 weeks

BUILDING USE

  • An open plan office
  • A QS office
  • A Site Managers office
  • A Meeting room
  • A Canteen
  • Toilet facilities
  • Shower facilities and changing area/drying room

CHALLENGES

The portable offices were to be installed with minimal disruption to the surrounding neighbourhood. We also had to take into consideration light pollution in the surrounding farmers’ fields which meant lights had to be strategically positioned to a particular angle.

OUTCOME

The modular buildings were installed to the client’s satisfaction and they were pleased with the overall appearance and finish of the buildings for this prestigious scheme.